from:China Electricity Councildate:2020-04-17
The pouring of the last layer of concrete for the outer containment dome of the K2 reactor's nuclear island at the Karachi nuclear power plant in Pakistan was finished on April 10, marking the successful capping of the structure, according to local reports.
Officials said the height of the reactor structure reaches 73.98 meters. It is the first overseas unit adopting the Hualong One nuclear reactor technology, also known as HPR 1000, a China-developed third-generation reactor design.
The K2 nuclear island has a double-layer containment and the outer containment is divided into a tubular structure and a dome structure.
Experts said that the capping of the outer containment dome laid a solid foundation for subsequent installation and debugging and the reactor's operation.
Tel:+86-25-84152563
Fax:+86-25-52146294
Email:export@hbtianrui.com
Address:Head Office: No.8 Chuangye Avenue, Economic Development Zone, Tianmen City, Hubei Province, China (Zip Code: 431700) Nanjing Office: Room 201-301, Building K10,15 Wanshou Road,Nanjing Area, China (Jiangsu) Pilot Free Trade Zone,Jiangsu Province,China (Zip Code:211899)