from:China Three Gorges Corporationdate:2019-12-30
The first turbine runner for the Karot Dam in Pakistan built by China Three Gorges Corporation (CTG) passed the ex-factory acceptance conducted during December 17 to 18.
During the two-day acceptance process, experts of the acceptance team performed appearance inspection, static balance testing, machining dimension inspection and non-destructive testing of welds for the runner, a core component of the hydro-turbine system, and all technical indicators turned out to be above the requirements specified in the contract.
The turbine runner weights 125.5 tons with a maximum diameter of 6.3m and a height of 3.3m. As the “heart” of the hydro-turbine, the runner is the core component that is vital to the efficiency, safety and stability of the system.
The acceptance of the first runner paves the way for manufacturing subsequent units of the Karot Dam, laying a solid foundation for the mechanical and electrical installation as well as commissioning of the project.
Tel:+86-25-84152563
Fax:+86-25-52146294
Email:export@hbtianrui.com
Address:Head Office: No.8 Chuangye Avenue, Economic Development Zone, Tianmen City, Hubei Province, China (Zip Code: 431700) Nanjing Office: Building 23, Baijiahu Science and Technology Industrial Park, No.2 Qingshuiting West Road, Jiangning Economic Development Zone, Nanjing City, Jiangsu Province,China (Zip Code:211106)