from:China General Nuclear Power Groupdate:2017-11-15
Concrete pouring for the raft foundation for the steam turbine of Fangchenggang Nuclear Power Plant (NPP) Unit 3 was completed on Nov 12.
The concrete pouring was completed hierarchically in about 40 hours by use of equipment from four directions -- north, south, east and west.
In order to ensure the pouring was a success, staff members of the project had been taking 24/7 shifts to monitor the whole process since the start of the pouring at 19:18 on Nov 10.
The raft foundation is located on a conventional island of Fangchenggang NPP, a Hualong One (HPR1000) demonstration project of China General Nuclear Power Corporation in Guangxi Zhuang autonomous region.
The success can be attributed to the mature cooperation between all parties involved, including engineers, installers and contractors.
Tel:+86-25-84152563
Fax:+86-25-52146294
Email:export@hbtianrui.com
Address:Head Office: No.8 Chuangye Avenue, Economic Development Zone, Tianmen City, Hubei Province, China (Zip Code: 431700) Nanjing Office: Room 201-301, Building K10,15 Wanshou Road,Nanjing Area, China (Jiangsu) Pilot Free Trade Zone,Jiangsu Province,China (Zip Code:211899)